West Carson Street Extension, Phase 3B – Stormwater Outfall
Project No: 12-408-79-1
Location: McKees Rocks, Allegheny County, PA
Owner: Borough of McKees Rocks
Manager: Doug Evans
Estimated Cost: $176,000
*Contract Awarded December 14, 2023
Contractor | Contact Person | Bid Amount |
---|---|---|
Borough of McKees Rocks 340 Bell Avenue McKees Rocks, PA 15136 |
LeeAnn Wozniak | N/A |
Jet Jack, Inc. 5020 Thoms Run Road Oakdale, PA 15071 |
Blaine Popp | $289,990.00 |
Quigley Development 211 Lesnett Road Pittsburgh, PA 15241 |
Jimalyn Ferguson | N/A |
Osiris Enterprises 2943 Brownshville Road Pittsburgh, PA 15227 |
Anthony Moscatiello | $185,055.00 |
Carmen Paliotta Contracting, Inc. 1550 Connor Road South Park, PA 15129 |
Pasquale Paliotta | N/A |
Friend Surface Solutions 187 Bradford Road Darlington, PA 16115 |
Garrett Friend | N/A |
Pride Masonry 1657 Evans City Road Evans City, PA 16033 |
Ken Maye | $194,958.00 |
S.E.T., Inc. 235 East Water Street Lowellville, OH 44436 |
Lindsey Sherrod | $194,283.80* |
DeMex LLC 125 Pflugh Road Butler, PA 16001 |
Jeff Langer | N/A |
G. Salandro Excavating, LLC 100 Honor Roll Drive Latrobe, PA 15650 |
Garrett Salandro | $222,150.00 |
Bid Advertisement
Sealed Bids are requested by the Borough of McKees Rocks at the Borough Manager’s office at 340 Bell Avenue, McKees Rocks, PA 15136 until 2:00 P.M. prevailing time, Thursday, November 30, 2023 for the West Carson Street Extension, Phase 3B – Stormwater Outfall. Bids will be opened publicly and read aloud immediately after the closing time for receipt of Bids.
Interested parties may view the Profile and Bid Schedule for this Project on the internet at: www.niraengineers.com.
Copies of the Bid Documents may be examined at the office of the Borough of McKees Rocks or at the office of NIRA Consulting Engineers, Inc., 950 Fifth Avenue, Coraopolis, Pennsylvania 15108. Copies thereof may be obtained from the office of NIRA Consulting Engineers, Inc., upon payment of a non-refundable sum of $70.00. An additional charge of $15.00 will be required for handling of Plans and Specifications when shipping is requested. Checks are to be made payable to NIRA Consulting Engineers, Inc. Bids must be submitted on the forms provided, and completed in strict accordance with the instructions provided. Each Bid must be accompanied by a Bid Bond, in the form of a Certified Check or Corporate Surety Bid Bond, in the amount of ten percent (10%) of the Bid Proposal made in the favor of the Borough of McKees Rocks. Only documents obtained directly from the Engineer will be valid at bid opening.
This project was financed in part by a grant from the Commonwealth of Pennsylvania, Commonwealth Financing Authority. The successful bidder will be required to comply with the requirements of the Grant Program.
A Performance Bond, Labor and Material Payment Bond, and Maintenance Bond in the amounts specified within the Contract Documents will be required of the successful Bidder.
Bidders on this work will be required to comply with the Provisions of the Pennsylvania Prevailing Wage Act 442. The Prevailing Wage Scale is included in these Specifications.
Bidders on this work will be required to comply with the Provisions of the Public Works Employment Verification Act (PWEVA).
Adherence to Instructions to Bidders is required.
No Bid or any part thereof shall be withdrawn by Bidder for a period of sixty (60) days subsequent to the Bid Opening.
The right is reserved by the Owner to reject any or all Bids or parts of bids and to waive technical defects in any Bid.
Project Scope
The proposed project includes the construction of ± 70 LF of 48 inch storm pipe and outfall structure. The project will include materials, demolition, excavation, installation, restoration, and all else necessary for a complete construction, as shown on the Contract Drawings.
Bid Schedule
Item No. | Description | Estimated Quantity |
Unit |
---|---|---|---|
1 | Mobilization, Bonds, Insurance, Shop Drawings, and Photo Documentation. | JOB | LS |
2 | Maintenance and Protection of Traffic. | JOB | LS |
3 | Erosion and Sediment Control. | JOB | LS |
4 | Bypass Pumping of Storm Flows. | JOB | LS |
5 | Exploratory Test Pit Excavations (As Directed). | 2 | EA |
6 | Demolition and Site Preparation. | JOB | LS |
7 | 48 Inch HDPE Pipe, 14-16 Foot Depth, Under Pavement (Includes Stone Backfill and Removal of Existing 36 Inch Pipe). | 68 | LF |
8 | Reconnect to Existing Pipe. | 1 | EA |
9 | Wall Support and Modifications. | JOB | LS |
10 | Earthwork (Includes Disposal). | JOB | LS |
11 | Type D Endwall. | 1 | EA |
12 | Rip-Rap Apron (R-5). | 31 | SY |
13 | Concrete Sidewalk Restoration. | 9 | SY |
14 | Concrete Driveway Restoration. | 24 | SY |
15 | Asphalt Pavement Restoration. | 58 | SY |
16 | Vegetative Restoration. | 300 | SY |
NIRA Consulting Engineers, Inc.
950 Fifth Avenue, Coraopolis, PA 15108
412.262.3970