West Carson Street Extension, Phase 3B – Stormwater Outfall

Project No:  12-408-79-1

Location:  McKees Rocks, Allegheny County, PA

Owner:  Borough of McKees Rocks

Manager:  Doug Evans

Estimated Cost:  $176,000

*Contract Awarded December 14, 2023

 

Contractor Contact Person Bid Amount
Borough of McKees Rocks
340 Bell Avenue
McKees Rocks, PA  15136
LeeAnn Wozniak N/A
Jet Jack, Inc.
5020 Thoms Run Road
Oakdale, PA  15071
Blaine Popp $289,990.00
Quigley Development
211 Lesnett Road
Pittsburgh, PA  15241
Jimalyn Ferguson N/A
Osiris Enterprises
2943 Brownshville Road
Pittsburgh, PA  15227
Anthony Moscatiello $185,055.00
Carmen Paliotta Contracting, Inc.
1550 Connor Road
South Park, PA  15129
Pasquale Paliotta N/A
Friend Surface Solutions
187 Bradford Road
Darlington, PA  16115
Garrett Friend N/A
Pride Masonry
1657 Evans City Road
Evans City, PA  16033
Ken Maye $194,958.00
S.E.T., Inc.
235 East Water Street
Lowellville, OH 44436
Lindsey Sherrod $194,283.80*
DeMex LLC
125 Pflugh Road
Butler, PA  16001
Jeff Langer N/A
G. Salandro Excavating, LLC
100 Honor Roll Drive
Latrobe, PA  15650
Garrett Salandro $222,150.00

Bid Advertisement

Sealed Bids are requested by the Borough of McKees Rocks at the Borough Manager’s office at 340 Bell Avenue, McKees Rocks, PA 15136 until 2:00 P.M. prevailing time, Thursday, November 30, 2023 for the West Carson Street Extension, Phase 3B – Stormwater Outfall.  Bids will be opened publicly and read aloud immediately after the closing time for receipt of Bids.

Interested parties may view the Profile and Bid Schedule for this Project on the internet at:  www.niraengineers.com.

Copies of the Bid Documents may be examined at the office of the Borough of McKees Rocks or at the office of NIRA Consulting Engineers, Inc., 950 Fifth Avenue, Coraopolis, Pennsylvania 15108. Copies thereof may be obtained from the office of NIRA Consulting Engineers, Inc., upon payment of a non-refundable sum of $70.00.  An additional charge of $15.00 will be required for handling of Plans and Specifications when shipping is requested.  Checks are to be made payable to NIRA Consulting Engineers, Inc. Bids must be submitted on the forms provided, and completed in strict accordance with the instructions provided.  Each Bid must be accompanied by a Bid Bond, in the form of a Certified Check or Corporate Surety Bid Bond, in the amount of ten percent (10%) of the Bid Proposal made in the favor of the Borough of McKees Rocks.  Only documents obtained directly from the Engineer will be valid at bid opening.

This project was financed in part by a grant from the Commonwealth of Pennsylvania, Commonwealth Financing Authority.  The successful bidder will be required to comply with the requirements of the Grant Program.

A Performance Bond, Labor and Material Payment Bond, and Maintenance Bond in the amounts specified within the Contract Documents will be required of the successful Bidder.

Bidders on this work will be required to comply with the Provisions of the Pennsylvania Prevailing Wage Act 442.  The Prevailing Wage Scale is included in these Specifications.

Bidders on this work will be required to comply with the Provisions of the Public Works Employment Verification Act (PWEVA).

Adherence to Instructions to Bidders is required.

No Bid or any part thereof shall be withdrawn by Bidder for a period of sixty (60) days subsequent to the Bid Opening.

The right is reserved by the Owner to reject any or all Bids or parts of bids and to waive technical defects in any Bid.

Project Scope

The proposed project includes the construction of ± 70 LF of 48 inch storm pipe and outfall structure.  The project will include materials, demolition, excavation, installation, restoration, and all else necessary for a complete construction, as shown on the Contract Drawings.

Bid Schedule

Item No. Description Estimated
Quantity
Unit
1 Mobilization, Bonds, Insurance, Shop Drawings, and Photo Documentation. JOB LS
2 Maintenance and Protection of Traffic. JOB LS
3 Erosion and Sediment Control. JOB LS
4 Bypass Pumping of Storm Flows. JOB LS
5 Exploratory Test Pit Excavations (As Directed). 2 EA
6 Demolition and Site Preparation. JOB LS
7 48 Inch HDPE Pipe, 14-16 Foot Depth, Under Pavement (Includes Stone Backfill and Removal of Existing 36 Inch Pipe). 68 LF
8 Reconnect to Existing Pipe. 1 EA
9 Wall Support and Modifications. JOB LS
10 Earthwork (Includes Disposal). JOB LS
11 Type D Endwall. 1 EA
12 Rip-Rap Apron (R-5). 31 SY
13 Concrete Sidewalk Restoration. 9 SY
14 Concrete Driveway Restoration. 24 SY
15 Asphalt Pavement Restoration. 58 SY
16 Vegetative Restoration. 300 SY
NIRA Consulting Engineers, Inc.

950 Fifth Avenue, Coraopolis, PA 15108
412.262.3970

© 2023 NIRA Consulting Engineers, Inc.